CESC solar project development in Rajasthan has reached a significant milestone, with 147 MW of the company’s 150 MW Bikaner solar power project commencing commercial operations on 21st November, 2026. The project is being developed by Deshraj Solar Energy Private Limited, a step-down subsidiary of CESC Limited at Village Karnisar Bhatiyan in Bikaner district.
The company informed the stock exchanges that the Commercial Operation Date (COD) was declared following a successful trial run certified by Grid Controller of India Limited’s Northern Regional Load Despatch Centre (NRLDC). The certification was issued on November 19, 2026.
The remaining 3 MW capacity is expected to be commissioned by January 31, 2027, taking the project’s total planned capacity to 150 MW.
CESC Solar Project Connected to Bikaner-III Substation
The 150 MW solar power project is located at Village Karnisar Bhatiyan in Bikaner district, Rajasthan. The project is connected to the Inter-State Transmission System (ISTS) through the Bikaner-III substation operated by Power Grid Corporation of India Limited (PGCIL).
With 147 MW now commercially operational, the project has achieved most of its planned capacity. The commissioning of the remaining 3 MW is expected to complete the project by the end of January 2027.
Also Read: MNRE Invites DISCOMs for DERMS Projects Under PM Surya Ghar Scheme
Grid Certification Marks Commercial Operation
The commencement of commercial operations followed the successful completion of the project’s trial run. Grid Controller of India Limited’s Northern Regional Load Despatch Centre certified the trial run through a certificate dated 19th November, 2026.
Based on this certification, Deshraj Solar Energy Private Limited declared November 21, 2026 as the COD for 147 MW of the project.
With 147 MW now operational and the remaining 3 MW expected by January 2027, CESC’s Bikaner solar project is nearing its full planned capacity of 150 MW.
Also Read: SWREL Bags ₹2,050 Crore Orders, Emerges L1 for Major Solar Project
Remaining 3 MW Expected by January 2027
While 147 MW has achieved commercial operation, the final 3 MW of the 150 MW solar power project is expected to be commissioned by 31st January, 2027.
The milestone marks progress in CESC’s solar project development through its subsidiary structure and adds operational renewable energy capacity in Rajasthan.
As the remaining capacity moves towards commissioning, the Bikaner project is expected to reach its full planned capacity of 150 MW in early 2027.